How we plan and track work

This is an outline of our new system for planning and tracking work at Life Itself. This is currently in transition and in the process of being implemented. Hereby the plan:

Summary

Every piece of work is written down in an allocated place. This picture shows where, and how.

HOW WE PLAN AND TRACK WORK

① [▤] RECORDS — THE SOURCE OF TRUTH
       one per initiative and project
       owner · status · tracker
       initiative: priority ★☆☆☆ to ★★★★
          │
          ├─▷ papers and tasks live in their
          │   own places; records link to them
          │
          └─▷ planning portfolio points to
              each project record
                   │
                   ▼
② [◷] TEAM PLANNING — WEEKLY OR FORTNIGHTLY
       Uriel + Rufus · Asdra deputy
       agree the plan and assign the work
       focus areas · owners · outcomes · main epic
       decide which projects matter this week
       improve the system in the same meeting
       save the plan in weeks/
          │
          └─▷ update initiative priority
              on the initiative record
                   │
                   ▼
③ [◉] YOUR WEEK
       your AI reads the records, trackers
       and team plan
       every item links to its source
       if they disagree, the record wins
  • Every initiative and project has one record: a short document with the work, its owner, its status and where its tasks are kept. The record is the source of truth.
  • We use 2 different tool trackers within Life Itself: the Media House uses Asana; everyone else (Ops; Planning; Community Events; PA Work) use Beads (see the Beads guide). Through Claude anyone can follow tasks across either task-tracking tool.
  • The team plan is a weekly or fortnightly note of what we agreed to focus on. See the plan for the week of 12 October. Read it for history; read a record for where things stand today.
  • Your AI builds your week from the records and task lists, linking every source. If they disagree, the records win. Only Media House (and their AI) changes Asana.

Prefer to watch? Play the 2-minute explainer above, or open it on the team Drive (draft, 22 Oct 2026; its source is in media/how-we-plan-video).

Tip: point your AI at this guide, don't paste it in. Open Claude in the planning folder on your computer, and tell it which files to read. For example:

Read guides/how-we-plan.md in the planning repository and tell me in five lines how we track our work.

Your AI can open any repository you have cloned, so you can point it at other folders the same way. Then ask it anything that isn't clear.

Where this stands: Implementing this plan is a pilot project from 22Oct - 5th Nov. Review is due 3Dec.

First Steps for Team Members: Get Set Up

  1. Clone the repositories you work on into one folder (see Where things live). Cloning means making a copy of a repository on your own computer, so you and your AI can read and change its files. Your AI can do it for you: ask it to clone the repository (follow the instructions here: GitHub explains it here).
  2. Set up your AI with this prompt: Use the planning skill. Run the sweep for me and show what's mine this week: in progress first, then ready, each with its priority and a link to its source.
  3. Use the recipes when you need them. Words you don't know are explained in Tools, who to ask, more detail.

1. The record holds the current truth

A project is work with an outcome and an end. An initiative is an ongoing area of work with no end date, such as Media House or Calls and Catalysts. Initiatives can sit inside each other: Calls and Catalysts is inside Gardens of Change, which is inside Seeds of Renaissance. Small tasks don't need a project, you can just log them to Beads.

Every project and initiative has one record. The record says what the work is, who owns it, where it stands, and where its tasks are. A project's record is a Markdown file in the projects/ folder of the project's repository. Open: Uriel is confirming this default. A repository is a folder of files kept on GitHub, with its full history of changes.

During the trial, a Media House project's record is its Asana project, not a Markdown file. Planning keeps a pointer to it: a short note that says where the record lives. We point to the record instead of copying it, so there is only one version to keep up to date.

Take the Global Connection Call, a new series of community calls run from the community repository (sor-community). Its record, as of 22 October:

 sor-community/projects/2611-…-global-connection-call-v1.md
 ──────────────────────────────────────────────────────────
 owner:         petronella
 status:        next
 parent:        calls-and-catalysts
 done_when:     first call 29 Oct; the series
                of six runs to 3 Dec
 tracker:       beads
 status_notes:  dated lines: what changed,
                who said so

What the fields mean:

  • owner: the person who confirms the facts in the record. Editing a file doesn't make you its owner.
  • status: in-progress means active now. next means chosen to start next. The data model lists the other words.
  • done_when: what finished looks like.
  • parent: the initiative this project sits inside.
  • tracker: where this project's tasks are kept: Beads or Asana.
  • status_notes: dated lines saying what changed and who said so.

Has the work stopped? Check the status. Work is paused or closed only when its status says so, with a dated note giving the reason (see Update a record or decision). An old date on its own doesn't mean the work has stopped. If the status still says active but nothing has moved for a while, ask the owner.

 [planning repository] (the central index)
 ├── initiatives/   one record per initiative,
 │                  with its repositories
 └── portfolio      a list built by the sweep:
        │           every project, its status,
        │           owner, and a link to its record
        │
        └──▷ sor-community/projects/2611-….md
             the record itself: this one wins

The central index is the planning repository. It keeps the initiative records and one list of every project. A sweep builds that list: a check that reads each project's record and puts them together in one place. If the list and a record disagree, the record is right.

The owner is the record's source: they confirm its facts. Editing a file doesn't make you its source.

Plan or record? The team plan is history: what we planned and decided, week by week. The record is today's state. Read a plan to see how we got here, and a record to see where things stand. Here is an example plan for the week of 12 October.

2. Where things live

Our office is a set of Git repositories in the life-itself organisation on GitHub, most of them private. Git is the system that keeps a history of every change to a set of files. If the office picture helps, read Post-its and filing cabinets first:

OfficeAt Life Itself
Rooman initiative
Cabineta repository, such as podcast or sor-community
Foldera project, in the cabinet's projects/ folder, with its papers
Central officethe planning repository: initiative records and a list of every project
Boardthe task tool where tasks live: Beads or Asana
Pointera short note pointing to work kept elsewhere
Note inside the doorAGENTS.md in each repository, with instructions for AI
Staff handbookthe Tao

Status key: Decided means agreed and in use. On trial means we're testing it until the review on 3 December. Open means nobody has decided yet. Until an open item is settled, follow the table and ask Uriel or Rufus.

WhatWhereStatus
Initiative recordsinitiatives/ in the planning repositoryDecided
Project recordsA Markdown file in the projects/ folder of the repository where the work happens, made with the portfolio skill. Projects about the planning system itself live in planning. During the trial, a Media House project's Asana project counts as its record. An A10 Google Doc is still allowed, with a pointer from planningOpen: Rufus's default, to confirm with Uriel
Index of every initiative and projectThe portfolio in planning: initiative records, plus a list of every project built by the sweep (Projects by initiative)Decided (sweep built 22 Oct)
Papers (reference material such as research and past notes)Markdown next to the project, in its repository. Move papers from Google Drive when you next work on that project, not all at onceDecided
DraftsWrite with your AI straight into Markdown. Use Google Docs only when drafting with others at the same timeOpen: Rufus's default, to confirm with Uriel
Media House tasksAsanaOn trial
Everything else: operations, infrastructure, code, planningBeads, the default. GitHub Issues is allowed but little used. Planning work goes in planning's Beads and initiative work in the initiative's repositoryOn trial. Which repository's Beads is open
Requests for Media HouseOne request inbox. Each request is one item with the required fields (see Ask Media House for something). You don't need Asana access to send one. Until the inbox is set up, send requests to UrielOn trial. The inbox is a file in the content repository, being set up by Uriel
Work that crosses teamsOne owning record. The other team holds one pointer. Promotion work is owned by its Media House task, and Beads holds a link if neededDecided. Written rule due 29 Oct
Team plansweeks/YYYY-MM-DD.md in planning, dated the MondayOn trial
Shared AI skills (written instructions your AI follows for a job)life-itself/skills, plus planning's own skills/Decided

Still open: the exact Asana line and where meeting notes go. Beads go in the repository where the work lives: Media House process and tools in mediahouse (prefix mh), specific pieces in content (prefix content), planning itself here (Rufus, 6 Nov 2026).

Where to log a new to-do. The Asana and Beads split is on trial.

 a new to-do
   │
   ├─ a request for        ──▷ the Media House
   │  Media House?             request inbox
   │
   ├─ Media House's        ──▷ Asana
   │  own work?
   │
   ├─ anything else?       ──▷ Beads: planning work in
   │                           planning's, initiative work
   │                           in the initiative's repo
   │
   └─ needs both teams?    ──▷ one team owns it;
                               the other gets one pointer

 not sure? ask Uriel (Media House) or Rufus

Who works where. Media House (Uriel, Amanda and Valerie) works in Asana. Operations and planning (Rufus, Asdra and Fae) work in Beads. Nobody outside Media House works in Asana, comments included. Anyone can read Asana, or ask their AI to report on it. Anything going public gets a one-line notice in Google Chat.

A cross-team example. A Wisdom paper release needs research and Media House promotion. The promotion goes to Media House as a request and is owned by its Media House task. The research stays in Beads, with a link to that task if needed.

Set up your folders. Clone the repositories you work on into one folder, so your AI can read across them:

 ~/code/life-itself/
 ├── planning/        the index, initiatives, weekly plans
 ├── podcast/         an initiative's projects and papers
 └── sor-community/   another initiative's projects and papers

3. The planning rhythm

Initiatives and projects are prioritised differently.

Each initiative has a priority rating of one to four stars. Uriel and Rufus agree and set these priorities centrally, and the rating is stored on the initiative record. Whenever a rating changes, a dated note must be added to the record stating who made the change. The priorities have been agreed, but they have not yet been entered on every initiative record.

Projects do not have a fixed, permanent priority. Instead, Uriel and Rufus decide which projects matter most as part of the weekly team planning process. These priorities are reflected in the team plan and can change from week to week.

To set priorities and agree the work, Uriel and Rufus will lead a weekly or fortnightly planning meeting, with Asdra acting as Uriel’s deputy. By the end of each week, Uriel, Rufus and Asdra will meet to run the planning sweep, agree on the team plan, assign each piece of work an owner, a next action, and a priority, and work on the system itself: creating projects, setting priorities, and improving the planning process. The plan will be saved in weeks/ and capture the team’s focus areas, owners, intended outcomes, and main epic for each area, rather than duplicating the task list. The 12 October plan provides an example, and the planning skill sets out the process.

   records (state) ──▷ sweep ──▷ team plan (flow)
        ▲                            │
        │                            ├──▷ work handed out
        │                            │    in the trackers
        └── initiative priority ◀────┘

Weekly planning (on trial). An AI helps us choose each week's projects and writes the week note. Weekly planning has the one prompt to start it.

This meeting and planning format are both on trial, and the meeting has not yet started regularly. Once it is running regularly, it will also be the place to brief the wider team on changes to how we work. Protecting time for planning and improving the system matters.

Anyone can ask their AI for a report on Asana, GitHub or Beads. Uriel pulls a full report across all three each week to see where operations stands.

Requests for Media House go to its request inbox (Recipes). Other requests, including Sylvie's, go to whoever handles that kind of work (see who to ask in Tools, who to ask, more detail).

4. Recipes

Start a project

No approval or Tao issue is needed.

  1. Check the portfolio first. Look at the planning portfolio to see whether the work already has a project or belongs to an existing one.
  2. Create or update the project record. Ask your AI to follow the portfolio skill and create the record in the projects/ folder of the repository where the work will live. The record should cover the intended outcome, owner, status, definition of done, tracker, and open questions. Add a pointer to the record in the planning portfolio so it can be found during the planning sweep.
  3. Plan substantial or new work. For larger projects or work that is new or not yet well-defined, use the project-planning skill to clarify the situation, complication, key question, and issue tree. This process is on trial; check with Rufus.
  4. Share the project record. Make sure the people whose time or shared resources the project needs have access to it.
  5. Create and assign the first task. Add the first task or epic to the appropriate tracker, assign an owner, and link it from the project record.

The goal: every project has a clear record, can be found through the portfolio, and has an owned first step.

Update a record or decision

  1. Change the facts that changed in the project's own record: owner, status, links, tracker (and priority, on an initiative).
  2. Add a dated line to status_notes saying what changed and how you know.
  3. Record a decision in the project's issue tree, as the question with a ✅ Answer., who decided and the date. Keep answered questions in place. Longer discussion goes in a file next to the record, linked from the answer. Design documents (such as voice or colour rules) hold the rule as applied and link back to the answer; they don't re-argue it.
  4. To pause or close work, change status and add a dated note with the reason. Keep the record.

The sweep picks up the change next time it runs; planning holds no copy to update. Edit your own project's record in its repository. In planning itself, Rufus, Fae and Asdra edit directly; anyone else can, when comfortable, or can send Rufus the link, the change and its source.

Log a task

  1. Find the right tracker with the diagram above.
  2. Ask your AI to check for an existing task before creating one.
  3. Give it an owner, a next action and a priority. The scales line up as Beads P0 to P2 = Asana high, P3 = medium, P4 = low. Owners matter most on epics and larger pieces; small sub-tasks don't each need one. Add a due date only when the date is genuinely fixed.
  4. Link it to its project.

Ask Media House for something

  1. Submit it to the Media House request inbox, one item per request. You don't need Asana access. The inbox is a file in the content repository, checked by a skill; until Uriel has set it up, send the same details to him.
  2. Include:
    • what's being promoted and who's asking
    • a short brief: what, why, audience, call to action
    • key dates: the event or launch, when promotion starts, the deadline
    • platforms
    • links and assets
    • who signs it off
  3. Uriel or someone in Media House goes through the inbox weekly and accepts the request (with an owner and a due date), asks you for what's missing, or declines it. Follow progress on that one item.
  4. If it's urgent, which should be rare, also message Uriel in Google Chat.

Ask the AI what's yours this week

  1. Open Claude in the planning repository, with your other repositories cloned alongside.
  2. Paste: "Use the planning skill. Run the sweep for me (my ID is ) and show what's mine this week: in progress first, then ready, each with its priority and a link to its source." Your ID is your file name in people, usually your first name in lower case.
  3. Open one or two of the links and check them. If the AI and the source disagree, the source wins: tell the AI and fix the record.
  4. The planning sweep doesn't include Asana or Google Docs yet, though your AI can read Asana if you ask it to. If you're in Media House, your week is in Asana (My Tasks) until the sweep includes it.

Clean up

  1. Ask: "Run the planning sweep and list the exceptions: stale, unowned, duplicated, finished but still open."
  2. The AI proposes fixes; a person confirms each one.
  3. Close finished work with a reason, merge duplicates, add owners, fix links on records.

Asdra will run this regularly outside Asana as a data-steward routine. The weekly view is only as good as the tasks behind it.

5. For AI agents

  • This guide is current. Where the README, the data model or older pages disagree with it, follow this guide. In particular, a project record is by default a Markdown file made with the portfolio skill, followed by the project-planning skill when needed; an A10 Google Doc is allowed but not the default, and during the trial a Media House project's Asana project counts as its record.
  • A project's own record, in its repository, is the source. Planning's cache may be stale: read the record itself before relying on it, and rerun the sweep when they differ.
  • The record schema is the data model. Use the portfolio skill for records; never edit portfolio/index.js.
  • Check for an existing record or task before creating one. Don't write to trackers or records without the person's confirmation.
  • On an open row, follow the current practice stated in the table, say that it is open, and ask before deciding anything new.
  • Cite the source (record path, task ID, Asana link) for every claim about tasks, owners or dates. Never fill a gap with a guess: an AI once gave a due date that did not exist in Asana.
  • Never copy tasks into the other team's tool; add one pointer. You may read Asana and report on it, but don't create, change or comment on anything there unless the person is in the Media House team. Requests for Media House go to its request inbox. Never write task lists into Markdown. Beads tasks follow the Beads conventions.
  • Most repositories are private: check sharing before sending or publishing a link.

6. Tools, who to ask, more detail

Claude (the desktop app's Code tab) is the main way in: you ask, and it reads and updates records and tasks. Set up your computer with the one prompt in Tao onboarding, which installs git, GitHub access and Beads. You rarely use Beads directly; the Beads guide explains how your AI does. Then read AI is the interface.

Ask Uriel about Media House, Asana, requests for Media House and the team plan; Rufus about records, Beads and shared skills; Asdra about clean-up; Fae about the planning site for collaborators who don't use these tools. Everyone's ID for owner: fields is in people.

Words used here:

  • Record: the one document for an initiative or project that says what it is, who owns it and where it stands.
  • Pointer: a short entry that points to a record or task kept somewhere else, instead of a copy.
  • Tracker: where tasks live, such as Beads or Asana. Beads is a task list your AI reads and writes for you.
  • Epic: a larger task that groups smaller ones.
  • Sweep: your AI reading across the records and trackers to list what is in progress, ready, stale or unowned.
  • Skill: a written set of instructions your AI follows for a job, such as the planning skill.
  • A10: an older Google Doc template for project plans, still allowed but no longer the default.

More detail: